Rehabilitation of High Pressure Heaters, Deaerator & Acid Cleaning Circuit of Ghorashal 55MW TPS Unit 1 – [2006 – 2007]
Client: TECHNOPROMEXPORT, Russia.
Piping & Electrical Works of one Boiler, Fabrication & Installation of Inlet Ducts of Two Boilers, Complete Hydro-testing Works of Four Boilers and supply of Technical Manpower & Equipment for Commissioning of 70MW Mymensingh CCPP – [2005 – 2006]
Client: Siemens Bangladesh Ltd.
Erection of Equipment, Supply of Materials, Fabrication, Erection, Painting, Insulation, Testing of all Piping, Chimneys, Intake & Exhaust Ducts, Platforms, Tanks etc. and assistance in commissioning of 10MWInsulation & Testing of Fire Fighting Pipeline, Supply, Fabrication & Installation of Cable Trays, Cable Ducts, HVAC System of Siddhirganj 21OMW TPS Project – [2002 – 2005]
Client: TECHNOPROMEXPORT, Russia.
Erection of Equipment, Supply of Materials, Fabrication, Erection, Painting, Insulation, Testing of all Piping, Chimneys, Intake & Exhaust Ducts, Platforms, Tanks etc. and assistance in commissioning of 10MW Combined Heat and Power Generation Station at Meghna Ghat – [2003]
Client: Energypac Power Generation Ltd.
Complete Construction of 6.6MW Diesel Power Plant at Bhola. The Jobs include Entire Civil & Building Work, Mechanical & Electrical Equipment Installation, Fabrication & Installation of Plant Piping, Construction of Fuel Storage Tanks, Instrumentation Works and assistance in Testing & Commissioning – [1987 – 1989]
Client: Bangladesh Power Development Board.
Complete Construction of 10,000MT Capacity Fuel Storage Tank, Electrical & Instrumentation Works of Khulna 11OMW Power Plant at Goalpara, Khulna- [1981 1982]
Client: Bangladesh Power Development Board.